PROJECT NAME |
LOCATION |
YEAR |
VOL |
|
MAIN CONTRACTOR |
OWNER/END USER |
|
|
|
|
|
|
|
IBRD Power XV Project |
East Java |
1990 |
156 |
t |
PT. Merlin Gerin Ind. |
PT. PLN |
|
|
|
|
|
|
|
Supporting Steel Structure |
East Java |
1991 |
150 |
t |
Siemens GmbH, Germany |
PT. PLN |
150 kV/500 kV Gresik CCPP |
|
|
|
|
|
|
|
|
|
|
|
|
|
Duri Kosambi & Suralaya |
West Java |
1992 |
900 |
t |
PT. MultiFabrindo |
PT. PLN |
Substation Project |
|
|
|
|
|
|
|
|
|
|
|
|
|
Supporting Steel Structure |
East Java |
1992 |
14 |
t |
Sprecher Energie Ltd. |
PT. PLN |
150 kV S/S Ujung |
|
|
|
|
|
|
|
|
|
|
|
|
|
Supporting Steel Structure |
Cilegon |
1992 |
20 |
t |
Siemens GmbH, Germany |
PT. PLN |
Kotabaja Extension, 150 kV |
|
|
|
|
|
|
|
|
|
|
|
|
|
Supporting Steel Structure |
Sumatera |
1992 |
22 |
t |
PT. GP Unindo Jaya |
CALTEX |
for Caltex Substation |
|
|
|
|
|
|
|
|
|
|
|
|
|
Belawan CCPP Block II |
North Sumatera |
1993 |
100 |
t |
Siemens GmbH, Germany |
PLN |
(430 MW), Switch-yard |
|
|
|
|
|
|
|
|
|
|
|
|
|
150 kV Transmission Line |
Java-Bali |
1993/1994 |
231 |
t |
Asea Brown Boveri AG. |
PT. PLN |
Java-Bali Stage I |
|
|
|
|
|
|
|
|
|
|
|
|
|
500 kV Transmission Line |
Java-Bali |
1993/1994 |
81 |
t |
Asea Brown Boveri AG. |
PT. PLN |
Cilegon-Cibinong-Saguling |
|
|
|
|
|
|
|
|
|
|
|
|
|
150 kV Transmission Line |
East Java |
1994 |
981 |
t |
Balfour Beatty Sakti Ind |
PT. PLN |
for Big Consumer Project |
|
|
|
|
|
|
|
|
|
|
|
|
|
500 kV Transmission Line |
West Java |
1994 |
600 |
t |
Asea Brown Boveri AG. |
PT. PLN |
Cilegon-Cibinong-Saguling |
|
|
|
|
|
|
|
|
|
|
|
|
|
150 kV Transmission Line |
West Java |
1994 |
290 |
t |
Asea Brown Boveri AG. |
PT. PLN |
Java-Bali, Stage I |
|
|
|
|
|
|
|
|
|
|
|
|
|
150 kV substation |
East Java |
1994 |
380 |
t |
Siemens AG, Germany |
PT. PLN |
Grati/Pasuruan CCPP |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Java |
1995 |
800 |
t |
PT. Multifab |
PT. PLN |
|
|
|
|
|
|
|
500 kV Substation |
West Java |
1995 |
540 |
t |
ABB Power Generation |
PT. PLN |
Muara Tawar CCPP |
|
|
|
|
|
|
|
|
|
|
|
|
|
150 kV Substation |
West Java |
1995 |
90 |
t |
PT. Abdi Bangun Buana |
PT. PLN |
Cikarang Listrindo Phase II |
|
|
|
|
|
|
|
|
|
|
|
|
|
150 kV Transmission Tower |
Central Java |
1995 |
400 |
t |
PT. Wijati Aji |
PT. PLN |
Rawalo - Semen Nusantara |
|
|
|
|
|
|
|
|
|
|
|
|
|
PLN Transmission Tower |
South Sumatera |
1995 |
270 |
t |
PT. Ciptanusa Castech |
PT. PLN |
70 kV Single & Double Sirkit |
|
|
|
|
|
|
|
|
|
|
|
|
|
150 kV PLN Transmission |
Central Java |
1996 |
120 |
t |
PT. Wijati Aji |
PT. PLN |
Tower ( Stub ) |
|
|
|
|
|
|
|
|
|
|
|
|
|
150 kV PLN Transmission Lines |
East Kalimantan |
1996 |
600 |
t |
PT. Mega Eltra |
PT. PLN |
Tarahan - Sutami |
|
|
|
|
|
|
150 kV Transmission Tower |
Jakarta |
1997 |
800 |
t |
PT. Wahanayasa Trans Energi |
PT. PLN |
Karet - Angke |
|
|
|
|
|
|
|
|
|
|
|
|
|
150 kV Switchyard Structure |
Pekanbaru |
1997 |
500 |
t |
Siemens AG |
PT. PLN |
|
|
|
|
|
|
|
150 kV T/L Suppa - Parepare |
Sulawesi |
1997 |
400 |
t |
PT. Citacontract |
PT. PLN |
|
|
|
|
|
|
|
150 kV Gantry for Lahendong |
North |
|
|
|
|
|
Power Plant 1 x 20 MW Project |
Sumatera |
1997 |
50 |
t |
Spie Enertrans |
PT. PLN |
|
|
|
|
|
|
|
500 kV Transmission Line Tower |
East Java |
1997 |
18,600 |
t |
BBL - BBSI - Joint Operation |
PT. PLN |
D/C Paiton - Kediri LOT 1 |
|
1998 |
|
|
|
|
|
|
|
|
|
|
|
500 kV Transmission Line Tower |
Central Java |
1997 |
17,900 |
t |
BBL - BBSI - Joint Operation |
PT. PLN |
D/C Kediri - Klaten LOT 2 |
|
1998 |
|
|
|
|
|
|
|
|
|
|
|
150 kV Gantry for Substation |
West Java |
1997 |
150 |
t |
PT. Multifab/PT. Meta Epsi Eng. |
PT. PLN |
|
|
|
|
|
|
|
150 kV T/L Sei Denai |
Sumatera |
1997 |
70 |
t |
PT. Wijaya Karya |
PT. PLN |
|
|
|
|
|
|
|
150 kV Substation Duri Kosambi |
Jakarta |
1999 |
40 |
t |
PT. Austrodwipa Energy |
PT. PLN |
|
|
|
|
|
|
|
275 kV T/L Sumatera |
Sumatera |
1999 |
14,000 |
t |
KEC International Ltd. |
PT. PLN |
|
|
2000 |
|
|
|
|
|
|
|
|
|
|
|
275 kV Transmission Lines Tower |
Sumatera |
1998 |
14,500 |
t |
KEC International Ltd. |
PT. PLN |
for South Sumatera |
|
1999 |
|
|
|
|
|
|
|
|
|
|
|
275 kV Transmission Lines |
Queensland Australia |
2000 |
30 |
t |
Kilpatrick Green |
POWERLINK QUEENSLAND |
Tower (Stub Tower Supply) |
|
|
|
|
|
|
|
|
|
|
|
|
|
275 kV Transmission Lines |
Queensland Australia |
2000 |
44 |
t |
Kilpatrick Green |
POWERLINK QUEENSLAND |
Tower (Stub Tower Supply) |
|
|
|
|
|
|
|
|
|
|
|
|
|
500 kV Trans. Lines Tower |
West Java |
2001 |
18,000 |
t |
BBL - BBSI - Joint Operation |
PT. PLN |
D/C Tasikmalaya - Depok |
|
2002 |
|
|
|
|
|
|
|
|
|
|
|
150 kV T/L RENUN HEPP |
Sumatera |
2001 |
140 |
t |
PT. Wisma Sarana Teknik |
PT. PLN |
|
|
|
|
|
|
|
500 kV T/L Tower Transmission |
Java - Bali |
2003 |
580 t |
ABB AG - Ajikawa - Joint Operation |
PT. PLN |
Tasikmalaya - Rawalo Bau - Klaten |
|
2004 |
|
|
|
|
|
|
|
|
|
|
|
Steel Structure and Gantries for |
East Java |
2003 |
800 |
t |
SIEMENS AG |
PT. PLN |
500/150 KV S/S, Tasikmalaya |
|
2004 |
|
|
|
|
|
|
|
|
|
|
|
Lot 15: 150 kV/TL South Sulawesi |
South Sulawesi |
2004 |
4,900 |
t |
ABB AG Power Line Division |
PT. PLN |
Supply, Fabrication, Galvanizing |
|
|
|
|
|
|
Tower Stub |
|
|
|
|
|
|
|
|
|
|
|
|
|
New Tasikmalaya Substation |
West Java |
2004 |
3,6 |
t |
PT. SIEMENS Indonesia |
PT. PLN |
|
|
|
|
|
|
|
Gantry, Beam & Equiptment |
West Java |
2005 |
130 |
t |
PT. SIEMENS Indonesia |
PT. PLN |
structure 150 kV Sentul Substation |
|
|
|
|
|
|
|
|
|
|
|
|
|
Maligi & Embalut Substation |
Indonesia |
2005 |
14 |
t |
PT. SIEMENS Indonesia |
PT PLN |
|
|
|
|
|
|
|
150 kV Substation Bulk Project 2005 |
Lombok |
2005 |
210 |
t |
PT. VATECH T&D |
PT PLN |
|
|
|
|
|
|
|
150 kV Gambir Lama Substation |
Jakarta |
2005 |
15 |
t |
PT. SIEMENS Indonesia |
PT PLN |
|
|
2006 |
|
|
|
|
|
|
|
|
|
|
|
150 kV T/L Jawa Bali Power |
Jakarta |
2007 |
2,580 |
t |
PT. Balfour Beatty Sakti Indonesia |
PT PLN |
Package IFB 3 A |
|
|
|
|
|
|
|
|
|
|
|
|
|
Gantry Tower Cikarang Listrindo |
Jakarta |
2007 |
26.5 |
t |
PT. SIEMENS Indonesia |
PT. Cikarang Listrindo |
Project |
|
|
|
|
|
Power Company |
|
|
|
|
|
|
|
Gantry Tower Cikarang Listrindo |
Jakarta |
2007 |
2.1 |
t |
PT. SIEMENS Indonesia |
PT. Cikarang Listrindo |
Project |
|
|
|
|
|
Power Company |
|
|
|
|
|
|
|
Gantry Tower Cikarang Listrindo |
Jakarta |
2007 |
1.7 |
t |
PT. SIEMENS Indonesia |
PT. Cikarang Listrindo |
Project |
|
|
|
|
|
Power Company |
|
|
|
|
|
|
|
Gantry Tower Tanjung Bunga |
Jakarta |
2007 |
9.5 |
t |
PT. SIEMENS Indonesia |
PT PLN |
Tallasa Project |
|
|
|
|
|
|
|
|
|
|
|
|
|
Paket 27: 150kV Transmission Line, Celukan Bawang Kapal |
Indonesia |
2008 |
1051 |
t |
PT. Balfour Beatty Sakti Indonesia |
PT PLN |
|
|
|
|
|
|
|
Project Kalimantan 150 Kv Package 3C |
Indonesia |
2008 |
113 |
t |
PT. Balfour Beatty Sakti Indonesia |
PT PLN |
|
|
|
|
|
|
|
Paket 5A Asahinas Menes |
Banten |
2008 |
674 |
t |
PT. Balfour Beatty Sakti Indonesia |
PT PLN |
|
|
|
|
|
|
|
Transmission Line 275 kV OHTL Medan - Galang Binjai ( Project Execution in 2008 ~ 2009 ) |
Indonesia |
2008 |
849 |
t |
PT. Balfour Beatty Sakti Indonesia |
PT PLN |
|
|
|
|
|
|
|
TOWER MENARA |
Indonesia |
2008 |
5.3 |
t |
PT. Berca Indonesia |
PT PLN |
|
|
|
|
|
|
|
Tower 150 Kv T/L PLTU 1 Jawa Barat-Kosambi Baru-Sukamandi |
West Java |
2008 |
700 |
t |
PT. Dalima Putra Perdana |
PT PLN |
Gardu Induk Muka Kuning Transmisi 4 CCT 150 KV |
Batam |
2008 |
97.2 |
t |
PT. Dalima Putra Perdana |
PT PLN |
|
|
|
|
|
|
|
Transmissi 4 CCT 150Kv Muka Kuning |
Batam |
2008 |
203.9 |
t |
PT. Dalima Putra Perdana |
PT PLN |
|
|
|
|
|
|
|
Gardu Induk Batakan & Tengkawang |
Kaltim |
2008 |
23 |
t |
PT. Dalima Putra Perdana |
PT PLN |
|
|
|
|
|
|
|
SUTT 150 Kv Asam Asam Mantuil section 2 |
Indonensia |
2008 |
332.6 |
t |
PT. Dalima Putra Perdana |
PT PLN |
|
|
|
|
|
|
|
SUBSTATION 150 KV Cikarang Listrindo |
West Java |
2008 |
13.4 |
t |
PT. SIEMENS Indonesia |
PT. Cikarang Listrindo Power Company |
|
|
|
|
|
|
|
Substation 170 Kv Kencana Alam |
Jawa |
2008 |
6.54 |
t |
PT. SIEMENS Indonesia |
PT PLN |
|
|
|
|
|
|
|
Substation 150 Kv Lolak-Kotamobagu |
Sulawesi |
2008 |
17.6 |
t |
PT. SIEMENS Indonesia |
PT PLN |
|
|
|
|
|
|
|
Raised Up Tower Muara Karang Gas Power Plant |
Muara Karang |
2008 |
108 |
t |
PT. SUMITOMO CORPORATION |
PT PLN |
|
|
|
|
|
|
|
Substation 150 kv Seputih Banyak |
Indonesia |
2008 |
107 |
t |
PT. SIEMENS Indonesia |
PT PLN |
|
|
|
|
|
|
|
Tower Transmission SUTT 150 kV Balaraja-New Balaraja |
Indonesia |
2008 |
327 |
t |
PT. Dalima Putra Perdana |
PT PLN |
|
|
|
|
|
|
|
Gardu Induk SUTT 150 kV Balaraja - New Balaraja |
Indonesia |
2008 |
34 |
t |
PT. Dalima Putra Perdana |
PT PLN |
|
|
|
|
|
|
|
SUTT 150 kV Patuha - Lagadar |
Indonesia |
2008 |
26 |
t |
PT. Dalima Putra Perdana |
PT PLN |
|
|
|
|
|
|
|
GITET 500 kV New Rawalo (Kesugihan) |
Indonesia |
2009 |
775 |
t |
PT. Citicon Adhi Nugraha |
PT. PLN |
|
|
|
|
|
|
|
150 KV Transmission Line, Celukan Bawang - Kapal |
Bali |
2009 |
743 |
t |
PT. Multi Fabrindo Gemilang |
PT. PLN |
|
|
|
|
|
|
|
SUTT 150 KV Transmission Line, Menes - GI Saketi - GI Rangkas |
Banten |
2009 |
1,172 |
t |
KSO Krakatau Engineering - Wisma Sarana Teknik - Wahayasa Trans Energi - Emsindo Pola Citra |
PT. PLN |
|
|
|
|
|
|
|
275 KV Transmission Line, Kiliranjao - Payakumbuh |
Sumbagsel |
2009 |
597 |
t |
PT. Dalima Putra Perdana |
PT. PLN |
|
|
|
|
|
|
|
275 KV Transmission Line, Kiliranjao - Payakumbuh |
Sumbagsel |
2009 |
452 |
t |
PT. Wahanayasa Trans Energi |
PT. PLN |
|
|
|
|
|
|
|
Substation 150 KV, Sengkang LNG |
Indonesia |
2009 |
159 |
t |
SIEMENS Pte, Ltd |
PT. PLN |
|
|
|
|
|
|
|
Substation 275kV/150kV Simangkuk |
Sumatera |
2009 |
237 |
t |
PT. SIEMENS Indonesia |
PT. PLN |
|
|
|
|
|
|
|
Gardu Induk Lahendong |
Indonesia |
2010 |
12 |
t |
PT. ABB Transmission & Distribution |
PT. PLN |
|
|
|
|
|
|
|
South Sulawesi Karebbe Hydroelectric Power Project (Gantry) Support Main Bus |
South Sulawesi |
2010 |
35 |
t |
PT. ABB Transmission & Distribution |
PT. PLN |
|
|
|
|
|
|
|
150kV Gantry Tanjung Kasam |
Batam |
2010 |
42 |
t |
PT. Batam Konektra Jaya |
PT. PLN |
|
|
|
|
|
|
|
SUTT 150kV Transmission Line, Batam |
Batam |
2010 |
36 |
t |
PT. Dalima Putra Perdana |
PT. PLN |
|
|
|
|
|
|
|
Gantry 150 kV Mliwang |
Indonesia |
2010 |
46 |
t |
PT. Dalima Putra Perdana |
PT. PLN |
|
|
|
|
|
|
|
SUTT 150 kV Sunyaragi - Brebes |
Indonesia |
2010 |
557 |
t |
PT. DaLima Putra Perdana |
PT. PLN |
|
|
|
|
|
|
|
Gantry 150 kV Ngimbang |
Indonesia |
2010 |
55 |
t |
PT. DaLima Putra Perdana |
PT. PLN |
|
|
|
|
|
|
|
Substation 500 kV Paiton 3 s/s Project |
Indonesia |
2010 |
89 |
t |
PT. Siemens Indonesia |
PT. PLN |
|
|
|
|
|
|
|
150kV T/L for Ulubelu Geothermal Power Plant Project (2x55 MW) |
Sumatera |
2010 |
850 |
t |
PT. Balfour Beatty Sakti Ind. |
PT. PLN |
|
|
|
|
|
|
|
T/L 150kV Kalimantan Package C 3 (Project Exection in 2010) |
Kalimantan |
2010 |
2,250 |
t |
PT. Balfour Beatty Sakti Ind. |
PT. PLN |
|
|
|
|
|
|
|
T/L 275 kV Galang Binjai OHTL - Medan (Project Execution in 2010) |
Medan |
2010 |
1,851 |
t |
PT. Balfour Beatty Sakti Ind. |
PT. PLN |
|
|
|
|
|
|
|
Transmission Line 275 kV Betung Aur Duri |
Indonesia |
2011 |
846 |
t |
PT. Dalima Putra Perdana |
PT. PLN |
|
|
|
|
|
|
|
T/L 150 kV Kalimantan Package C3 (Project execution in 2011) |
Kalimantan |
2011 |
2,052 |
t |
PT. Balfour Beatty Sakti Ind. |
PT. PLN |
|
|
|
|
|
|
|
T/L 150 kV - Banyuwangi (T.262 Watudodol) |
East Java |
2011 |
106 |
t |
PT. Wahayasa Trans Energi |
PT. PLN |
|
|
|
|
|
|
|
Gantry 500 kV Ngimbang 2, 150 kV Kediri 2, 150 kV Krian 4, dan 150 kV Grati 2 |
East Java |
2012 |
110 |
t |
PT. Hasta Karya Perdana |
PT. PLN |
|
|
|
|
|
|
|
150kV GI Cikarang Phase VII Project |
Cikarang |
2012 |
58 |
t |
PT. Siemens Indonesia |
PT. Cikarang Listrindo Power Company |
|
|
|
|
|
|
|
Tower 150 kV T/L Wotu - Malili Sec. 2 |
Indonesia |
2012 |
452 |
t |
PT. Menara Indra Utama |
PT. PLN |
|
|
|
|
|
|
|
GI 150 kV Rengat & Teluk Kuantan (ext) |
Sumatrera |
2012 |
86.21 |
t |
PT. TRUBA Engineering |
PT. PLN |
|
|
|
|
|
|
|
GI 70 kV Indorama Project |
Indonesia |
2012 |
22.32 |
t |
PT. ABB Sakti Industri |
PT. PLN |